Project Listing

  • Click on a column header to sort the table by that column. Click again to reverse the sort, and again to remove it. You can sort by multiple columns simultaneously.
  • Filter the table by entering a search term in the filter box at the top of the column that contains your search field. Select the filter criteria (starts with, contains, etc.) by clicking on the funnel next to the filter box. You can filter multiple columns simultaneously, and combine filters with sorts.
  • To group related records, drag the header for the column that you wish to segregate into groups into the blue bar at the top of the table (selected columns only). To ungroup, drag the column name out of the blue bar.
  • Clicking on the icons at the left of each record will provide access to bid information, detailed schedules, and photos when available.
  • For a definition of the different project statuses and phases please click here
Drag a column header and drop it here to group by that column
  StatusProject NumberPhaseSiteDescriptionCoordinatorContractorDesign ProfessionalConstruction StartSubstantial CompletionConstruction BudgetTypeAdmin Area
    
Data pager
Data pager
 Page 1 of 27, items 1 to 50 of 1320.
180181-PlanningBevisPainting & WaterproofingBenMooreConstruction Moisture Consulting, Inc.Kimszal Contracting, Inc. not recorded not recorded $432,000.00 Maintenance6
180401-PlanningCrestwoodRoof ReplacementBenMooreTBD (Continuing Services CM)TBD (Continuing Services Architect) not recorded not recorded not recorded Maintenance2
180291-PlanningHillsboroughSecurity VestibuleChuck PlanteNA (by others)Wilder Architecture, Inc. 6/11/2018 7/6/2018 $50,000.00 Site Work4
180341-PlanningJeffersonSecurity VestibuleChuck PlanteNA (by others)Ranon & Partners, Inc. 9/10/2018 12/28/2018 $100,000.00 Remodel1
180211-PlanningLeeNew/RebuildChuck PlanteJ E Dunn ConstructionFleischman-Garcia Architects and Planners, AIA, PA not recorded not recorded $9,371,600.00 Renovation4
180371-PlanningMintzRoof replacementBenMooreTBD (Continuing Services CM)Roof Engineering Associates, Inc. 4/3/2018 10/3/2018 $1,013,326.00 Planning5
180281-PlanningMultiple SitesMartinez/Steinbrenner Road WideningChuck PlanteNA (by others)Kisinger Campo & Associates Corp. 5/29/2018 6/29/2018 $5,000.00 Maintenance0
179991-PlanningMultiple SitesMisc. Minor Repair ProjectsMannyNA (multisite project)NA (in-house) not recorded not recorded not recorded Maintenance0
170071-PlanningNon-SBHC or Future SiteElementary DChuck PlanteAllstate Construction, Inc.Holmes Hepner & Associates Architects, Inc. not recorded not recorded $15,874,109.00 New Construction0
180391-PlanningNon-SBHC or Future SiteElementary EChuck PlanteTBD (CM Selection)TBD (Architect Selection) not recorded not recorded not recorded New Construction0
180381-PlanningPlantGym HVAC UpgradeJamesDieringerTBD (Continuing Services CM)Carastro & Associates, Inc. not recorded not recorded not recorded Maintenance1
180051-PlanningSchwarzkopfRoofingBenMooreSpringer-Peterson Roofing & Sheet Metal, Inc.C.B. Goldsmith & Associates, Inc. 5/26/2018 11/21/2018 $688,833.00 Maintenance2
180011-PlanningShawRoofingBenMooreSpringer-Peterson Roofing & Sheet Metal, Inc.Roof Engineering Associates, Inc. not recorded not recorded $1,128,546.00 Maintenance3
180351-PlanningTampa PalmsChiller ReplacementChuck PlanteDaikin Applied Americas Inc.TBD (Continuing Services Engineer) not recorded not recorded $155,083.00 Maintenance3
115071-Planningtest sitepaintingTBDNA (study only)NA (by others) not recorded not recorded not recorded Remodel5
150001-Planningtest site2Another test    not recorded not recorded not recorded Maintenance6
000002-DesignEast BayFront Entry (Phase 2)Chuck PlanteAjax Building CorporationWilder Architecture, Inc. 12/15/2015 8/9/2018 $655,087.00 Maintenance8
170192-DesignNon-SBHC or Future SiteHigh School TTTChuck PlanteCore ConstructionHarvard Jolly, Inc. 11/1/2018 7/24/2020 $49,000,000.00 New Construction0
180314-ConstructionAdamsChiller ReplacementJamesDieringerDaikin Applied Americas Inc.TBD (Engineer Selection) not recorded not recorded $186,537.00 Maintenance4
180334-ConstructionApollo BeachBlown-In Insulation RemovalMannyRW TYMEWELL, INC.NA (in-house) 8/30/2018 1/21/2019 $149,000.00 Site Work8
180094-ConstructionBrandonRoofingBenMooreTBD (Continuing Services CM)PBA Design Group, Inc. not recorded not recorded $40,000.00 Maintenance7
180234-ConstructionDurantCulinary Arts Classroom ConversionChuck PlanteWilliams Company TampaRowe Architects, Inc 5/29/2018 8/3/2018 $686,315.00 Remodel6
180034-ConstructionFolsomRoofingBenMooreCore Roofing Systems, Inc.C.B. Goldsmith & Associates, Inc. 5/26/2018 11/21/2018 $1,131,800.00 Maintenance7
180364-ConstructionJeffersonBleacher ReplacementBenMooreRW TYMEWELL, INC.NA (in-house) 9/24/2018 12/24/2018 $237,807.00 Planning1
180064-ConstructionLake MagdaleneRoofingBenMooreTBD (Continuing Services CM)Gale Associates South, Inc. 8/15/2018 11/15/2018 $967,552.00 Maintenance4
180134-ConstructionLithia SpringsRoofingBenMooreService Works Commercial Roofing, Inc.Roof Engineering Associates, Inc. 6/21/2018 11/21/2018 $662,413.74 Renovation6
170154-ConstructionMultiple SitesHurricane Hardening at 2 Sites (Erwin, McLane)Chuck PlanteR L BurnsRenker, Eich, Parks Architects, Inc. 3/7/2018 7/31/2018 $818,864.60 Renovation0
180324-ConstructionMultiple SitesRadon CorrectionsChuck PlanteCreative Contractors, Inc.ENGINEERING PROFESSIONALS INC 8/27/2018 not recorded $250,000.00 Site Work0
180144-ConstructionMultiple SitesThonotosassa/TBT Expoxy Pipe LiningTBDFlorida Pipe-Lining SolutionsTBD (Continuing Services Engineer) 5/29/2018 7/13/2018 $749,476.96 Maintenance0
180084-ConstructionNifong BuildingRoofingBenMooreTBD (Continuing Services CM)PBA Design Group, Inc. 11/13/2018 12/21/2018 $32,500.00 Maintenance6
180124-ConstructionPinecrestParking Lot DrainageMichaelBusciglioNA (by others)Kisinger Campo & Associates Corp. not recorded not recorded not recorded Maintenance6
180024-ConstructionThonotosassaRoofingBenMooreFlorida Pipe-Lining SolutionsRoof Engineering Associates, Inc. 7/25/2018 1/19/2019 $981,288.00 Maintenance7
11706-FinalAlonsoClassroom addition (12CR) and remodeling envelope observationJohn WilliamsConstruction Moisture Consulting, Inc.NA (in-house) 12/3/2015 7/25/2016 $18,684.00 New Construction2
180046-FinalCaminitiRoofingBenMooreRW TYMEWELL, INC.C.B. Goldsmith & Associates, Inc. 5/26/2018 11/21/2018 $1,310,656.43 Maintenance4
170386-FinalColsonChiller ReplacementMannyJohnson Controls, Inc.NA (in-house) 3/12/2018 3/16/2018 $184,027.33 Renovation7
170226-FinalCrestwoodHVAC Renovation MannyWalbridge Aldinger CompanySGM Engineering, Inc. 5/1/2018 7/31/2018 $2,450,034.92 Renovation2
170236-FinalCypress CreekHVAC RenovationChuck PlanteCreative Contractors, Inc.Lyle Engineering Group, Inc. 5/1/2018 7/31/2018 $2,883,689.54 Renovation8
180196-FinalDavisPainting & WaterproofingBenMooreC&C Painting Contractors IncConstruction Moisture Consulting, Inc. not recorded 8/20/2018 $173,597.53 Maintenance2
180106-FinalFreedomCooling TowerChuck PlanteTBD (Continuing Services CM)TBD (Continuing Services Engineer) 3/6/2018 6/25/2018 $390,700.00 Maintenance3
170426-FinalGorrieHVAC Replacement Phase 1Chuck PlanteCharles Perry Partners, Inc.ENGINEERING PROFESSIONALS INC 5/1/2018 8/6/2018 $1,923,975.68 Renovation1
180116-FinalHunters GreenParent Pick Up ImprovementsChuck PlanteNA (by others)Hamilton Engineering & Surveying, Inc. not recorded not recorded $26,000.00 Maintenance3
180246-FinalKenlywastewater/lift station replacementMichaelBusciglioNA (by others)Key Engineering Associates, Inc. not recorded 7/27/2018 $66,239.00 Renovation7
9476-FinalLambElementary BJill EdwardsBatson-Cook CompanyHolmes Hepner & Associates Architects, Inc. 10/20/2014 8/21/2015 $16,348,874.56 New Construction7
180226-FinalLeeWind BracingChuck PlanteHCBeck, Ltd. dba The Beck GroupMaster Consulting Engineers, Inc. 5/1/2018 8/2/2018 $706,732.88 Maintenance4
12126-FinalLomaxSign replacement (insurance claim)Jill EdwardsFlorida Sign Company, Inc.NA (design-build) 6/13/2016 9/22/2016 $9,820.00 Renovation4
170396-FinalMartinezChiller ReplacementMannyAir Mechanical & Service Corp.NA (in-house) 3/12/2018 3/16/2018 $290,997.00 Renovation2
180076-FinalMclaneRoofingBenMooreTBD (Continuing Services CM)Roof Engineering Associates, Inc. 12/12/2017 3/23/2018 $146,500.40 Maintenance7
170286-FinalMorgan WoodsHVAC RenovationMannyGilbane Building CompanyOssi Consulting Engineers, Inc. 5/1/2018 7/31/2018 $1,327,900.27 Renovation2
10506-FinalMullerJunior AchievementTBD CoordinatorNA (by others)NA (design-build) not recorded not recorded not recorded New Construction3
170376-FinalMultiple SitesGreenhouse Repairs at 3 Sites (East Bay, Steinbrenner, Strawbery Crest)Chuck PlanteRex Farlow Construction, Inc.NA (design-build) 11/13/2017 3/15/2018 $43,978.37 Remediation0